Bulanık CPM ile Doğrusal Programlama: İnşaat Endüstrisinde Bir Vaka Çalışması

dc.contributor.authorDeğirmenci, Güllü
dc.contributor.authorUĞURAL, MEHMET NURETTİN
dc.date.accessioned2023-04-14T11:48:39Z
dc.date.available2023-04-14T11:48:39Z
dc.date.issued2022
dc.description.abstractThe Critical Path Method (CPM) has been demonstrated to be a useful tool that is widely used in the construction industry for the planning and control of complex projects. However, because the duration of activities is represented as crisp numbers, it becomes difficult to precisely estimate the activity times in the critical path analysis. In addition, the majority of cases necessitate the subjective calculation of task duration times, resulting in ambiguity about the duration of the activities. This paper addresses these issues by proposing an approach based on fuzzy sets. The purpose of this study is to demonstrate how to use fuzzy numbers to calculate the critical path and completion time of a construction project. Two distinct solution algorithms were constructed by giving triangular fuzzy durations to the project activities within the scope of the study. The critical path and project duration of a sample construction project were calculated in the first solution algorithm by assigning triangular fuzzy durations to project activities and using the linear programming model, whereas the fuzzy project time and critical path were calculated in the second solution algorithm by using the Alpha cutting method (α - Cutting Method) and then clarified using the Centroid method (COA- Center of Area). Because the critical path and completion time for this project are known ahead of time, the two solution algorithms were compared. It is hoped that using the FCPM method rather than the CPM method will highlight the significance of this study.en
dc.identifier10
dc.identifier.citationDeğirmenci G, UĞURAL M (2022). BULANIK CPM İLE DOĞRUSAL PROGRAMLAMA: İNŞAAT ENDÜSTRİSİNDE BİR VAKA ÇALIŞMASI. Mühendislik Bilimleri ve Tasarım Dergisi, 10(2), 466 - 481. 10.21923/jesd.949954
dc.identifier.doi10.21923/jesd.949954
dc.identifier.issn1308-6693
dc.identifier.trdizin1135078
dc.identifier.urihttps://doi.org/10.21923/jesd.949954
dc.identifier.urihttps://hdl.handle.net/11413/8460
dc.language.isotr
dc.publisherSüleyman Demirel Üniversitesi Mühendislik Fakültesi
dc.relation.journalMühendislik Bilimleri ve Tasarım Dergisi
dc.rightsinfo:eu-repo/semantics/openAccess
dc.rights.urihttp://creativecommons.org/licenses/by-nc-nd/4.0/
dc.subjectBulanık CPM
dc.subjectİnşaat Mühendisliği
dc.subjectLineer Programlama
dc.subjectYapım Yönetimi
dc.subjectProje Yönetimi
dc.titleBulanık CPM ile Doğrusal Programlama: İnşaat Endüstrisinde Bir Vaka Çalışmasıtr
dc.title.alternativeLinear Programming With Fuzzy Cpm: A Case Study in Construction Sectoren
dc.typeArticle
dspace.entity.typePublication
dspace.relatedentity.typePerson
local.indexed.atTrDizin
local.journal.endpage481
local.journal.issue2
local.journal.startpage466
person.identifier.orcid0000-0002-8037-7603
relation.isAuthorOfPublicationdd14cf99-05d7-4852-b417-dbdb4c5fe8de
relation.isAuthorOfPublication.latestForDiscoverydd14cf99-05d7-4852-b417-dbdb4c5fe8de

Files

Original bundle

Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
Tam Metin/Full Text
Size:
1.32 MB
Format:
Adobe Portable Document Format

License bundle

Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.82 KB
Format:
Item-specific license agreed upon to submission
Description: